Charles Street
Find the latest information, schedules, and timelines on the Charles Street elevator modernization project.
project overview
In 2019, building condition assessments were conducted for Charles Street to inform how we prioritize major capital work, including upgrades to the elevators in both 30 and 35 Charles.
To conduct this work, one elevator will be taken out of service at a time, and it is expected that it will take 10-12 weeks to modernize each elevator. As a result, the building will only have 3 operating elevators during this modernization period. Once an elevator is modernized and 100% complete, they will start work on another elevator.
Review the weekly schedule
Please note that elevator bookings can take place between 10am-4pm and 6pm to 10pm.
On-Site
Upgrades
We understand that having one of our elevators out of service for a prolonged period is not welcoming news, but these repairs and upgrades are necessary as major components of the existing elevators are nearing the end of their lifecycle. We want to proactively improve the reliability and performance of this crucial equipment, and introduce modern features including:
wayfinding
To assist with elevator traffic levels, we advise to take the stairs when/if possible. Below are two wayfinding maps to make accessing the stairs at 30 Charles easier.
Elevator Bookings
With one elevator unavailable at 30 Charles for the foreseeable future, residents are advised to expect longer wait times. There may also be times when the service elevator is booked temporarily, leaving only two elevators available. Whenever possible, we advise residents to allocate additional time when leaving or returning to the building, avoid busy travel times, and if able to, use the stairs.
Increased elevator bookings take place during the first and last week of every month to accommodate move-ins and move outs.
We will be posting an up-to-date elevator booking schedule every Monday which outlines the next week’s elevator bookings. Please note that this schedule is subject to last minute changes.
Week of: December 23rd, 2024 | ||||||
---|---|---|---|---|---|---|
Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | Sunday |
2pm - 4pm | ||||||
Updated As of December 23rd, 2024 |
30 charles Elevator Modernization
This is the current construction schedule from Direct Elevator, the company who will be conducting the elevator modernization project.
To conduct this work, one elevator will be taken out of service at a time, and it is expected that it will take 10-12 weeks to modernize each elevator. As a result, the building will only have 3 operating elevators during this modernization period. Once an elevator is modernized and 100% complete, they will start work on another elevator.
Elevator 2 | Elevator 3 | Service Elevator | Elevator 4 |
---|---|---|---|
APRIL-JULY | JULY-SEPTEMBER | OCTOBER – DECEMBER | DECEMBER – MARCH |